Mongomeyen Airport, Equatorial Guinea

Project

From 2006 to 2012, Ceo of TCM Sarl participated at the construction of the Mongomeyen International Airport. It was a turnkey Project , Airport Category CAT I R, Aircraft of Reference B747 with a traffic Estimation of 1.500.000 Passengers per year. The scope of work comprised 3,7 million m³ earthworks, a runway of 3.000 m X 60 m, taxiways, apron of 107.000 m² , road network of 8,2 km, Water supply  and Waste water network, Control Tower and 8 technical buildings with a total surface of approx. 30.000 m², delivery and installation of the entire energy supply, communication, FIDS, meteorological, and landing system with equipment such as: ILS, VOR-DME, NDB..

Client:

The Final Beneficiary was the Government of Equatorial Guinea, represented by the Presidency of the Republic, GE-Proyectos and the Ministry of n of Civil Aviation..
A Consortium of international Construction companies headquartered in Germany was awarded to build the Airport.

Contract Value and Results

EUR 227,1 MILLIONS
The was completed within the time schedule, The result and elaboration were delivered to the client’s satisfaction.

Pictures